Another update from Casey J. Graham, P.E.
As I am sure everyone is aware, the Contractor continues to work on removing the old asphalt and building the shoulder further down South Bogan to allow all traffic to move onto the temporary road.  This will enable the contractor to remove the rest of the old road bed and start the next phase of work. 
 
We continue to work with the engineer-of-record to get a plan revision finalized to alter the traffic shift in front of your subdivision.   I have also passed on the request to have our Signals Group (headed up by Chuck Bailey) perform a Signal Warrant Study for the entrance onto South Bogan, but as I said, I do not think there will be enough traffic.  Also, I have given the request to our Design Group for consideration of a dedicated left into the subdivision for the next SPLOST program, as we are not installing one as a part of our work.